Seven months of improvement work on Ilford train line to start next week

PUBLISHED: 16:10 19 August 2013 | UPDATED: 16:24 19 August 2013

Commuters on the platform at Seven Kings station

Commuters on the platform at Seven Kings station

Archant

Seven months of improvement works on the train line through Ilford and Seven Kings is starting next week.

Network Rail is installing new foundations, steel masts and power lines along the track “to enable trains to run more efficiently and safely”.

The work will be carried out on weekends between Stratford and Seven Kings from August 30 until March 31.

People living and working in properties next to the track have been warned of possible disruption, although the “noisiest work” is scheduled only on Sundays and bank holidays between 8am and 8pm.

To avoid affecting train services, the upgrade will mostly be done at night weekends and over the Christmas holidays.

In a letter to residents, Network Rail community relations manager Rupal Patel said: “The equipment we use means some disturbance is unavoidable but we will make every effort to minimise any unnecessary noise.”


If you value what this story gives you, please consider supporting the Ilford Recorder. Click the link in the orange box above for details.

Become a supporter

This newspaper has been a central part of community life for many years. Our industry faces testing times, which is why we're asking for your support. Every contribution will help us continue to produce local journalism that makes a measurable difference to our community.

Latest from the Ilford Recorder